How MARTA rail came to Atlanta, 1975 to 1988

From a 1965 act to a 1971 vote, then construction in 1975, the first trains in 1979 and the airport station in 1988: how Atlanta got its rapid transit system.

The first MARTA train carried passengers on June 30, 1979, running east and west between Georgia State University and Avondale. One argument ended that day and another began. The one that ended was whether a region built around cars and interstates would put up a subway at all, a fight that had played out in the Georgia General Assembly and at the ballot box since 1965. The one that began was over what the system would cover, who would pay and who would ride, and it is still going.

What follows traces the system from the act that created it, through the first trains and the north-south line, to the opening of the airport station in 1988. It stays with the decisions: who voted, what they voted for and what the vote left out.

1965: an agency before a line

The Metropolitan Atlanta Rapid Transit Authority, MARTA, was created in 1965 by the Georgia General Assembly as a proposed rapid-transit agency for five counties: DeKalb, Fulton, Clayton, Gwinnett and Cobb. That year four of the five, Clayton, DeKalb, Fulton and Gwinnett, together with the City of Atlanta, approved participation. Cobb's referendum failed.

Money was the problem. A 1968 referendum to fund the system failed. Not until 1971 did voters in Fulton and DeKalb counties approve a 1 percent sales tax for MARTA operations. Voters in Clayton and Gwinnett rejected it, and Gwinnett has stayed outside the system ever since. More than any other single event, the 1971 vote fixed the shape of MARTA: a two-county system centered on Atlanta, with a regional name and a regional plan but a local tax base.

The reasons the other counties gave, and the debates around those votes, belong to historians of the region, and different accounts weigh them differently. The factual record is simple: Fulton and DeKalb voted yes; Clayton, Gwinnett and, earlier, Cobb did not. You can see the result on today's map. MARTA rail stops inside the Perimeter and runs north along two branches, but not into Cobb or Gwinnett. See Inside and outside the Perimeter: what ITP and OTP mean for how that geography shows up in daily life, and The 2017 sales tax rise that funded Atlanta's MARTA share for how the funding changed later.

Who voted for what

Jurisdiction 1965 vote on participating 1971 vote on the 1 percent sales tax
City of Atlanta Approved Part of Fulton and DeKalb counties, which approved
Fulton County Approved Approved
DeKalb County Approved Approved
Clayton County Approved Rejected
Gwinnett County Approved Rejected
Cobb County Referendum failed no vote noted here

Read across the rows and the table explains the present system. Two counties paid, so two counties got rail. Gwinnett, which approved participation in 1965 and then rejected the tax in 1971, has stayed outside. Cobb never joined. The 1965 vote shows broad regional interest in the idea of rapid transit, and the 1971 vote shows that interest narrowing to the two counties willing to tax themselves for it.

The decade in dates

Year Event
1965 The General Assembly creates MARTA for five counties
1968 A funding referendum fails
1971 Fulton and DeKalb approve the sales tax; MARTA agrees to buy the bus company
February 17, 1972 The bus purchase closes; MARTA begins running buses
1975 Rail construction begins
June 30, 1979 First trains run, Georgia State to Avondale; Five Points opens later that year
1981 North-south line opens, including Midtown
December 15, 1984 Lindbergh Center opens; the line runs Brookhaven to Lakewood/Fort McPherson
1988 The airport station opens

1972: buses first

The first thing MARTA did with its money was buy buses. In 1971 the agency agreed to purchase the Atlanta Transit Company, the private operator that had run the city's buses, and the sale closed on February 17, 1972, giving MARTA control of public transit in the immediate Atlanta area. Bus operations under MARTA began that day. Buses were the part of the network residents could use years before the first train.

The purchase also fixed something about MARTA's identity: from its first day the agency was both a bus and a rail operator, and the two were meant to feed each other. A rider on a feeder bus would transfer to the train. That design remains; the transfer rules in MARTA fares in 2026: a worked example for a week of riding describe how it works now.

1975: the digging begins

Construction of the heavy-rail system began in 1975. That is the year the agency's historians and the standard accounts use, and it marks the point at which the plan became a worksite. The initial segment was to run east and west through Downtown, with a north-south line planned to cross it at a central station.

The central station was Five Points, the hub where the two lines meet. It stands at the point from which the railroad that gave the city its name was measured in 1837, as described in Five Points and the zero milepost, where the railroad made a city, so the transit system's crossing point and the city's founding point are the same place. The Five Points hub opened later in 1979, after the first trains were already running.

June 30, 1979: the first trains

Rail service began on June 30, 1979, with an east-west line from Georgia State University to Avondale. By later standards it was a short line, but it did what a first segment had to do: carry passengers through Downtown and out to the east, and prove the system worked. The Five Points hub opened later that year. The opening is where the story of MARTA's trains starts, and also where the debate shifted from whether to build to where to extend.

Georgia State University gave the line its western anchor, and the university's later growth is covered in Georgia State University and the first MARTA line: a Downtown campus on the train.

1981 to 1984: the north-south line

The second major phase was the north-south line. It opened in 1981, with service across Downtown and into Midtown, where the subway arrived in 1981 and helped bring the redevelopment described in Midtown: Atlanta's vertical neighborhood. By 1984 the line ran from Brookhaven to Lakewood/Fort McPherson. Along the way, Lindbergh Center station opened on December 15, 1984, at the point where the north line would later fork; its story is in Lindbergh/Morosgo: a transit village in Buckhead.

The north-south line followed the Peachtree ridge from the center of the city toward Buckhead, the axis of the three skylines covered in Atlanta's three skylines: Downtown, Midtown and Buckhead compared.

1988: the airport

In 1988 the line was extended to a station inside the airport terminal. It is one of MARTA's best-known features, and it makes Atlanta one of the large American cities where a traveler can step from a plane to a train without leaving the terminal complex. The station remains on today's Red and Gold lines, and the practical details of the trip are in Getting from Hartsfield-Jackson to Downtown, Midtown and Buckhead by MARTA and MARTA to the airport: the line that put a terminal on the train.

What the first decade of construction cost

The shape of the funding is clear even without a single total: the 1 percent sales tax approved in 1971 in Fulton and DeKalb counties was the foundation, supplemented by other sources of capital. The sales-tax rate within the City of Atlanta rose later, with the More MARTA program approved by voters in November 2016, which added half a percent and brought the city's rate to 1.5 percent in 2017. In February 2020, all four jurisdictions approved keeping the full 1 percent through 2057, rather than stepping it down in 2047. Those later decisions are discussed in the article on the 2017 rate rise.

Everything that came later

Several other milestones belong in any timeline:

The system by the numbers

As of 2026, the rail system has about 48 miles of track and 38 stations in four lines, and it is run by a board with members from Atlanta, Fulton, Clayton and DeKalb, plus nonvoting representatives of the state transportation department and the Georgia Regional Transportation Authority. MARTA is a joint powers authority, not a department of any one government.

What the history teaches

Three lessons come out of 1965 to 1988. First, transit in a car-oriented region is as much a political achievement as an engineering one. It took two decades to get from act to train, and the vote of 1971 settled the system's geography for good. Second, a rapid-transit system, once built, shapes development around its stations; Midtown, Buckhead and the airport corridor all changed after the trains arrived. Third, the system's limits, including its two-county tax base, were set at the start and are still visible. A rider who boards at Five Points and travels north is on a line whose route was chosen in the 1970s and whose reach was decided by voters in 1971, a connection to the past that few commuters ever think about.